Earlcoate Construction Ltd.
Fawley Power Station
1600m2 / 400m3 (two pours)
Co-ordinate all stages of industrial flooring project to specification & deadline
We were recently contracted by Earlcoate Construction Ltd. for an early morning job at Fawley Power Station to place a power floated concrete floor. The concrete was supplied by Breedon and was delivered in 5 loads before 7am. We then placed 1600m2 / 400m3 of concrete flooring in two pours at 250mm deep to get the job done, ensuring that our contractor was successfully able to meet their client’s demands.
We are the leading concrete flooring contractors in the UK, offering outstanding concrete finishing results with every project. For more information about our services, contact our team today on 01590 676 585.