Barnwood Construction
Honeybourne Place, Cheltenham
7,588m2
Our scope of works included:
Close collaboration with both Barnwood Construction and the delivery teams ensured timely progress without disruption to the surrounding environment. Our proactive approach helped maintain site flow and keep the build programme on track.
We recently completed a six-storey metal decking installation for Barnwood Construction in Honeybourne Place, Cheltenham. The site's central location, adjacent to a large Waitrose supermarket made logistics a key challenge. However, with careful planning and collaboration, our team successfully delivered the project across three structured phases.
Following each decking and studding phase, our concrete flooring team took over to prepare and pour the reinforced slab. This included:
In addition to the upper floors, we also completed the ground floor slab, which featured over 80 tonnes of bar reinforcement, demonstrating our full-package delivery from deck to finish.
Looking for a reliable contractor for your next commercial or industrial build? Whether you're planning a multi-storey structure or need a full concrete flooring package, we're here to help. Call our team on 01590 676 585 or get in touch online to discuss your metal decking requirements.